Sethness Roquette Food Ingredients (Lianyungang) Co., Ltd Project - China

Capacity

-

Location

China

Completion date

2012

Work scope: 

  • Caramel production site with a capacity of 45000 tons / year; 

  • 1 workshop of 1150m2; 

  • 1 storehouse of 920m2; 

  • 1 administration building and workshop of 450m2; 

  • 1 waste water treatment plant of 440m2; 

  • 1 emergency pool of 230m2; 

  • Steel pipeline of 350m, medium pressure steam pipeline of 650m; 

  • Other works such as tanks foundations, external platforms. 


Services: 

  • Basic design 

  • Construction Design 

  • Technical assistance to the approval process

  • Technical assistance at site (Resident engineers) As-built drawings

Related expertises