Hydropower Project of Gouina - 140MW
140MW
Capacity
Location
Mali
2020
Completion Date
Work scope:
A concrete gravity dam with an overflowing spillway over the entire length of 560 m;
A headrace channel of 290m long;
A powerhouse equipped with 3 Kaplan turbine-generator units with a total capacity of 140MW;
A tailrace channel of 90m wide and 395m long;
A transmission line of 225kV and about 58 km long;
Two 225kV switchyards: 1 to be built, 1 to be extended.
Services:
Alternative Studies for the preparation of technical proposal;
Technical and commercial support for contract negotiation;
Review and advice of Basic and Construction design;
Related expertises