Hydropower Project of Gouina - 140MW

140MW

Capacity

Location

Mali

2020

Completion Date

Work scope:

  • A concrete gravity dam with an overflowing spillway over the entire length of 560 m;

  • A headrace channel of 290m long;

  • A powerhouse equipped with 3 Kaplan turbine-generator units with a total capacity of 140MW;

  • A tailrace channel of 90m wide and 395m long;

  • A transmission line of 225kV and about 58 km long;

  • Two 225kV switchyards: 1 to be built, 1 to be extended.


Services:

  • Alternative Studies for the preparation of technical proposal;

  • Technical and commercial support for contract negotiation;

  • Review and advice of Basic and Construction design;

Related expertises

Related projects

Beijing Address 

28A, Shangdi Information Road, Keshi Plaza, Tower C-07A

Haidian District, Beijing China 100085

Hong Kong Address

Level 54 Hopewell Center,

183 Queen's Road East

Wan Chai, Hong Kong

Paris Address

58 rue de Monceau CS 48756

75008 Paris , France

bottom of page