Kariba North Bank - Kafue West 330kV Transmission Project
Capacity
330 kV
Location
Zambia
Completion date
2014
Work scope:
135km long 330kV transmission line from Kariba North Bank Substation to Kafue West Substation
Extension of 330kV line bay in Kariba North and Kafue West Switchyard
Services:
Foundation design, steel tower design, electrical design and earthing design;
Consultant service work for the 330 kV transmission line including tower erection, conductor stringing work, equipment erection, testing, commissioning work and all other related works
Basic Design and Construction Design of the extension 330kV existing switchyard and filed testing and commissioning.